Govia Thameslink Railway 872M23

View line Govia Thameslink Railway

Daily Govia Thameslink Railway

✓ Today’s run finished

Today, last fix heading to Shepherds Bush at 09:29 −2 min

The mini-map returns when the train runs
On-time · 30 days
73%
22/30 runs under 3 min
RT coverage: 30 full · 0 partial · 0 no data
On-time · 90 days
78%
70/90 runs under 3 min
RT coverage: 90 full · 0 partial · 0 no data
Typical delay
0min
Median at arrival, 90 days
30 days: 0 min
P90
+7min
9 in 10 runs arrive with less than this
30 days: +7 min

Last 30 days

Delay at the end of each run, in minutes. One bar per run.

  • On time (<3 min)
  • 3–10 min
  • 10–30 min
  • 30+ min
  • Partial coverage
  • No data

Worst days

  • Mon 21 Sept Max en route +16 min · last fix heading to Chessington South +15 min
  • Mon 28 Sept Max en route +17 min · last fix heading to Chessington North +13 min
  • Wed 29 Jul Max en route +15 min · last fix heading to Chessington South +13 min
  • Thu 1 Oct Max en route +11 min · last fix heading to Chessington North +11 min
  • Mon 7 Sept Max en route +10 min · last fix heading to Chessington South +9 min

Distribution · 90 days

90 runs with a known final delay. On time = under 3 min, the same cut the map uses.

  • Early 2% · 2
  • On time 76% · 68
  • 3–10 min 18% · 16
  • 10–30 min 4% · 4
  • 30+ min 0% · 0

On-time by weekday

  • 58% M n=12
  • 85% T n=13
  • 69% W n=13
  • 85% T n=13
  • 85% F n=13
  • 92% S n=13
  • 69% S n=13

Recent runs

DateLast stopFinalMax
Sun 11 OctShepherds Bush 09:29−2 min—
Sat 10 OctChessington South 11:29−1 min+2 min
Fri 9 OctChessington South 11:300 min+9 min
Thu 8 OctChessington South 14:420 min+1 min
Wed 7 OctChessington North 11:300 min+6 min
Tue 6 OctChessington South 14:28+6 min+8 min
Mon 5 OctChessington South 11:19−1 min+4 min
Sun 4 OctChessington North 11:40+5 min+5 min
Sat 3 OctChessington South 11:32+2 min+3 min
Fri 2 OctChessington South 11:29−1 min+2 min
Thu 1 OctChessington North 15:05+11 min+11 min
Wed 30 SeptChessington North 11:33+3 min+5 min
Tue 29 SeptChessington South 14:200 min+7 min
Mon 28 SeptChessington North 14:39+13 min+17 min
Sun 27 SeptChessington South 11:34−1 min+3 min
Sat 26 SeptWatford Junction 10:31+1 min+4 min
Fri 25 SeptChessington South 11:33+3 min+6 min
Thu 24 SeptChessington South 14:160 min+7 min
Wed 23 SeptChessington South 11:300 min—
Tue 22 SeptChessington South 11:30+1 min+5 min
Mon 21 SeptChessington South 15:17+15 min+16 min
Sun 20 SeptShepherds Bush 09:34+2 min+3 min
Sat 19 SeptWatford Junction 10:300 min—
Fri 18 SeptWatford Junction 10:320 min+1 min
Thu 17 SeptChessington North 11:37+7 min+8 min
Wed 16 SeptChessington South 11:290 min+6 min
Tue 15 SeptChessington South 11:29−1 min+10 min
Mon 14 SeptChessington South 11:30+1 min+5 min
Sun 13 SeptChessington South 11:33−2 min+3 min
Sat 12 SeptChessington North 11:32+2 min+4 min

Each run is closed into train_runs (country, train number, service day) from the live positions. Final delay = last delay seen. Partial coverage: the feed stopped before the final stop (last value used, hatched in the chart). No data: a run without any valid delay; counts as neither on time nor late. Data collected since 11 July 2026.