Os 27201 27201 Luby u Chebu – Cheb

View line Os 27201

Luby u Chebu 04:36 → Cheb 05:12 Mon, Tue, Wed, Thu, Fri 0 h 36 min · 10 stops České dráhy, a.s.

✓ Today’s run finished

Today, last fix heading to Cheb at 05:13 No data

  1. Luby u Chebu04:36
  2. Nový Kostel04:42
  3. Velký Luh04:48
  4. Vonšov04:56
  5. Nový Drahov04:59
  6. Tršnice05:04
  7. Cheb05:12

Next service: tomorrow 04:36 from Luby u Chebu · Fri 6 Nov

Next departure 04:36 tomorrow · Luby u Chebu
On-time · 30 days
—
Too little data (0/21 runs with data)
RT coverage: 0 full · 0 partial · 21 no data
On-time · 90 days
78%
31/40 runs under 3 min
RT coverage: 40 full · 0 partial · 22 no data
Typical delay
0min
Median at arrival, 90 days
P90
+4min
9 in 10 runs arrive with less than this

Last 30 days

Arrival delay at Cheb, in minutes. One bar per run.

  • On time (<3 min)
  • 3–10 min
  • 10–30 min
  • 30+ min
  • Partial coverage
  • No data

Worst days

  • Mon 14 Sept Max en route +32 min · last fix heading to — +31 min
  • Tue 15 Sept Max en route +10 min · last fix heading to — +10 min
  • Fri 2 Oct Max en route +4 min · last fix heading to — +4 min
  • Thu 1 Oct Max en route +4 min · last fix heading to — +4 min
  • Fri 18 Sept Max en route +4 min · last fix heading to — +4 min

Distribution · 90 days

40 runs with a known final delay. On time = under 3 min, the same cut the map uses.

  • Early 0% · 0
  • On time 78% · 31
  • 3–10 min 18% · 7
  • 10–30 min 3% · 1
  • 30+ min 3% · 1

On-time by weekday

  • 88% M n=8
  • 75% T n=8
  • 88% W n=8
  • 75% T n=8
  • 63% F n=8
  • — S n=0
  • — S n=0

Stops and timetable

Timetable of the latest run from the operator’s GTFS (10 stops).

Last 90 days, 40 runs. At intermediate stops it is an estimate from the delay at origin and destination. Delays over 2 h count as “> 2 h”: our data does not measure them exactly.

StopSched.Usually 9 days in 10
04:36on time on time
04:39≈ on time ≈ on time
04:42≈ on time ≈ +1 min
04:48≈ on time ≈ +1 min
04:53 / 04:54≈ on time ≈ +2 min
04:56≈ on time ≈ +2 min
04:59≈ on time ≈ +3 min
05:01≈ on time ≈ +3 min
05:04 / 05:05≈ on time ≈ +3 min
05:12on time +4 min

Each run is closed into train_runs (country, train number, service day) from the live positions. Final delay = last delay seen. Partial coverage: the feed stopped before the final stop (last value used, hatched in the chart). No data: a run without any valid delay; counts as neither on time nor late. Data collected since 11 July 2026.

Will I make my connection?

Pick where you get off and how many minutes you have until your next train. We work it out from what this train did over the last 90 days.

Include the time to change platforms. It is an estimate from past data, not a guarantee. Days more than 2 h late count as a missed connection.

Recent runs

DateLast stopFinalMax
Thu 5 NovCheb 05:13No data—
Wed 4 NovCheb 05:13No data—
Tue 3 NovCheb 05:14No data—
Mon 2 NovCheb 05:13No data—
Fri 30 OctCheb 05:13No data—
Thu 29 OctCheb 05:13No data—
Tue 27 OctCheb 05:13No data—
Mon 26 OctCheb 05:13No data—
Fri 23 OctCheb 05:13No data—
Thu 22 OctCheb 05:13No data—
Wed 21 OctCheb 05:13No data—
Tue 20 OctCheb 05:13No data—
Mon 19 OctCheb 05:13No data—
Fri 16 OctCheb 05:13No data—
Thu 15 OctCheb 05:13No data—
Wed 14 OctCheb 05:13No data—
Tue 13 OctCheb 05:13No data—
Mon 12 OctCheb 05:13No data—
Fri 9 OctCheb 05:13No data—
Thu 8 OctCheb 05:13No data—
Wed 7 OctCheb 05:13No data—
Tue 6 OctCheb 05:13No data—
Mon 5 Oct— 05:270 min—
Fri 2 Oct— 05:32+4 min+4 min
Thu 1 Oct— 06:06+4 min+4 min
Wed 30 Sept— 05:31+3 min+3 min
Tue 29 Sept— 05:31+3 min+3 min
Fri 25 Sept— 05:32+3 min+3 min
Thu 24 Sept— 05:290 min+1 min
Wed 23 Sept— 05:280 min—